I. Valley Road Sewer and Water Relay
This is a continuation of the sewer and water work that began in Fall, 2024. This work is being done ahead of the Valley Road Reconstruction project, which is anticipated to take place in 2026 by Winnebago County. Click here to access the original project post.
Contractor: PTS Contractors, Inc.
Anticipated Completion Date: Early May 2025
II. Clayton Avenue Sewer and Water Extension

This project will extend public sanitary sewer and water along Clayton Avenue from Shady Lane to approximately a half mile north of Shady Lane. The purpose of this project is to have public sanitary sewer and water available for proposed and future development projects in the Village. Additionally, a stormwater culvert just north of Shady Lane is in poor shape and will be replaced.
Clayton Avenue will be CLOSED TO THRU TRAFFIC between Shady Lane and Wrenwood Lane. Local traffic will still be able to access their property in this area. Vehicles are recommended to use Irish Road or STH 76 for detours.
Contractor: Jossart Brothers
Anticipated Start Date: April 9, 2025
Anticipated Completion Date: Late June 2025
III. Margeo Stormwater Pond and Utility Construction

This project is considered to be the largest project of the 2025 construction season for the Village and will consist of two concurrent parts:
- Constructing a new stormwater retention pond at the northwest corner of CTH CB and Winchester Road (CTH II).
- Relaying sanitary sewer main and water main as well as installing some storm sewer in the Margeo Acres East Subdivision.
The purpose of the stormwater retention pond is to assist the Village with long-term Municipal Stormwater Permit compliance with the Wisconsin DNR and assist the Village with meeting stormwater regulations for reconstruction of Irish Road, which is anticipated to be done in 2027.
For the Utility Construction, sanitary sewer and water main will be replaced in the subdivision due to aging infrastructure. Additionally, storm sewer will be installed out to Irish Road in anticipation of the Irish Road Reconstruction project.
Click here to view PowerPoint presentation slides from the April 3, 2025 Public Information Meeting.
Contractors: MCC, Inc (Pond); DeGroot, Inc (Utilities)
Anticipated Start Date: Late Mid-May 2025 (Pond); Mid-May/Early June 2025 (Utilities)
Anticipated Completion Date: Early October 2025 (Pond); Early November 2025 (Utilities)
IV. Winchester Road Reconstruction

This project will consist of reconstruction of Winchester Road from the railroad tracks to North Lake Street. As part of the project, the pavement, gravel base, and curb and gutter will be replaced. Storm sewer piping and inlet structures will also be replaced with the project. The finished road will be a 2-lane road, with 14-foot driving lanes and 6-foot shoulders.
2-way traffic is anticipated to be maintained as part of this project. It is possible that the railroad may be reconstructing the Winchester Road crossing around the same time as this project, but a schedule has not been confirmed with the railroad yet.
Contractor: Northeast Asphalt, Inc
Anticipated Start Date: TBD
Anticipated Completion Date: TBD
V. 2025 Asphalt Program




This project is part of the Street Department’s annual program to re-pave Village roads that are in poor condition. This year, the project will consist of two parts:
- Wedge and Overlay Streets
- Asphalt Resurfacing
The following streets will receive the Wedge and Overlay treatment:
- Shady Lane (Olde Buggy Lane to Cold Spring Road)
- Ehlers Road (Railroad to Haase Street)
- Mayer Street
- William Street
- Claude Street
- Ann Street
The Wedge and Overlay treatment consists of removing and replacing only the top 1.5 – 2 inches of asphalt. The purpose of this is to extend the life of the streets a few more years until more substantial reconstruction of the streets can be completed.
The following streets will receive the Asphalt Resurfacing treatment:
- Millbrook Drive
- Eagle Drive
- Oxwood Drive
- Cricket Court
- Pages Point Road
- Palisades Drive (Palisades Drive to Annex Lane)
- Annex Lane
- Olde Midway Road (Lakeshore Drive to Racine Road)
- Wittmann Drive (Wittmann Park Lane to Appleton Road)
The following trails will receive the Asphalt Resurfacing treatment:
- American Drive Trail (Shady Lane to Prospect Avenue)
The Asphalt Resurfacing treatment consists of fully removing the existing asphalt pavement, doing spot repairs on the gravel base, and putting new asphalt pavement down.
Contractor: MCC, Inc.
Anticipated Start Date: TBD
Anticipated Completion Date: TBD
VI. Sanitary Sewer Lining

Fox Crossing Utilities is planning to line sanitary sewer in portions of the Glenview Park Subdivision. This project will consist of installing a Cured-in-Place liner that will adhere to the existing sanitary sewer pipe. The purpose of this project is to reduce groundwater inflow and infiltration into the Village’s sanitary sewer system.
Contractor: TBD
Anticipated Start Date: TBD
Anticipated Completion Date: TBD
VII. Asphalt Crack Seal Program
This project is part of the Street Department’s annual program to seal cracks that have formed in asphalt pavement. Ideally, this is done a few years after a road is resurfaced, though it depends on the road condition. Stay tuned for more information on streets anticipated to be crack sealed.
Contractor: TBD
Anticipated Start Date: April 28, 2025
Anticipated Completion Date: Mid-July 2025 (except for E Shady Lane)
VIII. Concrete Street Repair
This project is part of the Street Department’s annual program to repair sections of the Village’s concrete roads where significant cracks have formed. Stay tuned for more information on streets where this work will occur.
Contractor: TBD
Anticipated Start Date: TBD
Anticipated Completion Date: TBD